Project Name |
Job Description |
Scope of Work |
Tonnage |
CLIENT |
LOCATION |
1 |
Yanbu III Power & Desalination Plant |
Electro Static Precipitator |
Shop Drawing & Fabrication |
1495 |
SWCC |
Yanbu |
2 |
Yanbu III Power & Desalination Plant |
Sea Water Flue Gas Desulphurization
System (SWFGD) |
Shop Drawing & Fabrication |
3540 |
SWCC |
Yanbu |
3 |
Yanbu
III Power & Desalination Plant |
Air
and Gas Duct |
Shop
Drawing & Fabrication |
2800 |
SWCC |
Yanbu |
4 |
Duba
Power Plant |
Pipe
Spools |
Shop
Fabrication |
61 |
SEC |
Duba |
5 |
Qassim Power Plant |
Pipe
Spools |
Shop
Fabrication |
90 |
SEC |
Qassim |
6 |
Shuqaiq Steam Power Plant |
Carbon Steel BOP Pipe Spool |
Shop
Fabrication |
3371 |
SEC |
Shuqaiq |
7 |
Shuqaiq Steam Power Plant |
HFO/HCO
Pipe Spools |
Shop
Fabrication |
7285 |
SEC |
Shuqaiq |
8 |
Qassim Power Plant Ext. |
Exhaust Gas Stack System including Diverter Tee Box, Duct &
Blanking Guillotine |
Shop
Drawing & Fabrication |
2652 |
SEC |
Qassim |
9 |
Power
Plant #13 & 14 (PP13/14) |
Exhaust Gas Stack System
including Diverter & Duct |
Shop
Drawing &Fabrication |
1344 |
SEC |
Riyadh |
10 |
Wasit
Gas Plant |
Supply of 6 Nos. Chemical Storage
Tanks |
Design, Shop Drawing & Fabrication |
|
ARAMCO |
Jubail |
11 |
King
Abdul Aziz International Airport |
Supply of Pipe Supports to
various area at Load Center A, B & C |
Shop
Drawing & Fabrication |
1261 |
Ministry of Aviation |
Jeddah |
12 |
Jeddah South Power Plant |
Supply of Pipe Spool |
Shop
Drawing & Fabrication |
8500 |
SEC |
Jeddah |
13 |
Jeddah South Power Plant |
Supply of Embeded Steel Items |
Shop
Drawing & Fabrication |
350 |
SEC |
Jeddah |
14 |
King
Abdulla University for Science & Technonlogy (KAUST) at Thuwal |
Supply of Fuel Oil Tanks (3 Nos.) |
Design, Shop Drawing & Fabrication |
16 |
ARAMCO |
Thuwal - Jeddah |
15 |
Arar
Power Plant |
Exhaust Gas Stack System including Diverter Tee Box & Duct |
Shop
Drawing &Fabrication |
230 |
SEC |
Arar |
16 |
Mataf
Extension |
Safa
Bridge Zone C Trusses D2 D8 |
Shop
Drawing, Fabrication & Installation |
1591 |
Ministry |
Makkah |
17 |
Power
Plant #10 (PP10) CCP |
Steel
for Air Cooled Condensers - Fin Fan |
Shop
Drawing and Fabrication |
200 |
SEC |
Riyadh |
18 |
Power
Plant #12 (PP12) |
Structural Steel Items Fan Screen to Air Cooled Condenser (ACC) |
Shop
Drawing and Fabrication |
215 |
SEC |
Riyadh |
19 |
Power
Plant #10 (PP10) CCP |
Structural Steel Items Fan Screen to Air Cooled Condenser (ACC) |
Shop
Drawing and Fabrication |
505 |
SEC |
Riyadh |
20 |
Power
Plant #12 (PP12) |
Steel
Duct, Risers & Manifold for Air Cooled Condenser (ACC) |
Shop
Drawing and Fabrication |
791 |
SEC |
Riyadh |
21 |
Power
Plant #12 (PP12) |
Air
Cooled Condenser Tanks - 2 Nos. |
Shop
Drawing and Fabrication |
|
SEC |
Riyadh |
22 |
Power
Plant #12 (PP12) |
Exhaust Gas Stack System
including Diverter Tee Box & Duct for 8 Units |
Shop
Drawing, Fabrication and Installation |
294 |
SEC |
Riyadh |
23 |
Power
Plant #10 (PP10) CCP |
Air
Cooled Condenser Tanks - 10 Nos. |
Shop
Drawing and Fabrication |
|
SEC |
Riyadh |
24 |
Power
Plant #10 (PP10) CCP |
Non
Pressure Part including transition duct for Vertical HRSG |
Shop
Drawing &Fabrication |
17145 |
SEC |
Riyadh |
25 |
Shoaiba II - CCP |
Steel
Structures for 10 Units Exhaust Stack |
Shop
Drawing & Fabrication |
270 |
SEC |
Shoaiba |
26 |
Qurayyah Combined Cycle Plant |
Vertical HRSG for 3 Nos. of Boilers |
Shop
Drawing & Fabrication |
2190 |
SEC |
Qurayyah |
27 |
Qurayyah Combined Cycle Plant - Block 6 |
CCW
Expansion Tanks |
Shop
Drawing & Fabrication |
13 |
SEC |
Qurayyah |
28 |
Qurayyah Combined Cycle Plant |
CSRL
Piping & Fittings for Condensate and Pump Discharge Sides - 6
Blocks |
Shop
Drawing and Fabrication |
822 |
SEC |
Qurayyah |
29 |
Qurayyah Combined Cycle Plant - Block 6 |
Miscellaneous Service Building
Structres |
Shop
Drawing and Fabrication |
280 |
SEC |
Qurayyah |
30 |
Al
Jouf Power Plant |
Exhaust Gas Stack System including Diverter Tee Box & Duct for 4
units |
Shop
Drawing &Fabrication |
85 |
SEC |
Al
Jouf |
31 |
Rafha
Power Plant |
Supply & Delivery of Exhaust System for Two Gas Turbine |
Shop
Drawing &Fabrication |
140 |
SEC |
Rafha |
32 |
Tabouk Power Plant Ext. |
Exhaust Gas Stack System including Diverter Tee Box & Duct |
Shop
Drawing &Fabrication |
150 |
SEC |
Tabouk |
33 |
Qurayyah Combined Cycle Plant - Phase C |
Pipe
Rack Structure at STG Area for 3 Blocks |
Shop
Drawing, Fabrication & Installation |
6200 |
SEC |
Qurayyah |
34 |
Qurayyah Combined Cycle Plant - Phase C |
Steam
Turbine Building for 5 Blocks |
Shop
Drawing, Fabrication & Installation |
6400 |
SEC |
Qurayyah |
35 |
Al
Qassim Power Plant Ext. |
Exhaust StExhaust Gas Stack System including Diverter Tee Box |
Shop
Drawing &Fabrication |
1120 |
SEC |
Qassim |
36 |
Power
Plant No. 10 (PP10) |
Exhaust Gas Stack System including Diverter Tee Box & Duct |
Shop
Drawing &Fabrication |
1112 |
SEC |
Riyadh |
37 |
Makkah - Clock |
Steel
Structure for Elevators HP41
& HP42 at Tower H Level 391.7 to 450.15) |
Shop
Drawing, Fabrication & Installation |
80 |
DOKAAE |
Makkah |
38 |
Qurayat Power Plant |
Exhaust Gas Stack System including Diverter Tee Box & Duct |
Fabrication & Installation |
98 |
SEC |
Qurayat |
39 |
Hail
Power Plant |
Exhaust Gas Stack System including Diverter Tee Box & Duct |
Fabrication & Installation |
98 |
SEC |
Hail |
40 |
King
Abdullah Financial District |
Steel
Structure for Hotel at 10 & 11th Floors |
Shop
Drawing, Fabrication & Installation |
470 |
Ministry of Finance |
Riyadh |
41 |
New
Doha Inaternational Airport |
Steel
Structures & Water Storage Tanks |
Shop
Drawing & Fabrication |
715 |
Ministry of Aviation |
Doha,
Qatar |
42 |
Princes Nora Bid Abdul Rahman University for Women |
Steel
Domes, Lecture Hall Bldg Steel Structure and Canopy |
Shop
Drawing, Fabrication & Installation |
565 |
Ministry of Education |
Riyadh |
43 |
King
Abdullah International Conference Center |
Steel
Domes and Structures |
Design, Shop Drawing, Fabrication and Installation |
1600 |
Ministry of
Cutural & Information |
Jeddah |
44 |
King
Saud University |
Steel
Roof Structures for Buildings and Skylight Supporting Structures |
Design, Shop Drawing, Fabrication and Installation |
2700 |
Ministry of Education |
Riyadh |
45 |
Power
Plant #10 (PP10) |
Steel
Pipe Racks, Walkways, Handrails, Ladder & Gratings |
Connection Design, shop Drawing, Fabrication and Installation |
1350 |
SEC |
Riyadh |
46 |
Power
Plant #10 (PP10) |
Steel
Building/Shed Structures for Transformer, Generators, Parking
& other Utilities. |
Shop
Drawing, Fabrication and Installation |
2200 |
SEC |
Riyadh |
47 |
Power
Plant #10 (PP10) |
Steel
Storage Tanks |
Design, Shop Drawing, Fabrication and Installation |
1650 |
SEC |
Riyadh |
48 |
Power
Plant #10 (PP10) |
Steel
Building Structures for Turbine Building A1, B1, A2, B1, B1 |
Connection Design, shop Drawing, Fabrication and Installation |
7100 |
SEC |
Riyadh |
49 |
Power
Plant #10 (PP10) |
Exhaust Gas Stack System
including Diverter Tee Box & Duct for 36 Units Gas Turbine |
Shop
Drawing, Fabrication and Installation |
1444 |
SEC |
Riyadh |
50 |
Qurayyah Combined Cycle Plant |
Steel
Walkways, Platform,
Ladders, etc. |
Shop
Drawing & Fabrication |
270 |
SEC |
Qurayyah |
51 |
Qurayyah Combined Cycle Plant |
Field
Fabricated Steel Storage Tanks (18 Nos.) |
Design, Shop Drawing, Fabrication
& Installation |
2440 |
SEC |
Qurayyah |
52 |
Qurayyah Combined Cycle Plant |
20
Nos. Air Receivers (ASME Stamped) |
Design, Shop Drawing & Fabrication |
80 |
SEC |
Qurayyah |
53 |
Qurayyah Combined Cycle Plant |
Steel
Structures for Technical & Non-Technical Buildings |
Shop
Drawing, Fabrication & Installation |
1955 |
SEC |
Qurayyah |
54 |
Massa
Extension – Safa & Marwa |
Enlarged Steel Bridge at Grid 50 and M8 |
Shop
Drawing, Fabrication & Installation |
147 |
Ministry of Hajj |
Makkah |
55 |
Massa
Extension – Safa & Marwa |
Steel
Structure for first & second floors for Handicapped |
Shop
Drawing, Fabrication & Installation |
857 |
Ministry of Hajj |
Makkah |
56 |
King
Abdullah University for Science
& Technology |
Steel
Building Structures |
Shop
Drawing & Fabrication |
1700 |
MOHE |
Tuwal,
Jeddah |
57 |
Shuqaiq Power Plant |
3
Nos. Flow Contact Scrubbers & HVAC Duct Supports |
Shop
Drawing & Fabrication |
466 |
ARAMCO |
Shuqaiq |
58 |
Shuqaiq Power Plant |
3
Nos. Emergency Storage Tank,
3 Nos. Air Receivers & 3 Nos. Boiler Blow Tanks |
Shop
Drawing & Fabrication |
60 |
ARAMCO |
Shuqaiq |
59 |
PP9
Blocks F |
Thermal Storage Tank |
Design, Shop Drawing & Fabrication |
650 |
SEC |
Riyadh |
60 |
PP9
Blocks C, D & F |
Pipe
Racks, Building Structures, etc. |
Shop
Drawing & Fabrication |
443 |
SEC |
Riyadh |
61 |
Fujairah Power Plant |
GCB
Structure for GT Circuit Breaker, Pipe Rack Structures & Support
Structures |
Shop
Drawing & Fabrication |
187 |
IWPP |
Fujairah, UAE |
62 |
Madinah Haram Piazza Shading |
Umbrella Foundation for Car Parking |
Shop
Drawing & Fabrication |
145 |
Ministry of Hajj |
Madinah |
63 |
Safwa
Cement Plant |
Steel
Structure & Plate Works |
Shop
Drawing & Fabrication |
805 |
Safwa
Cement Co. |
Safwa,
Jeddah |
64 |
Juaymah Gas Plant (Aramco) |
Support Steel Structure, Pipe
Racks, |
Shop
Drawing & Fabrication |
210 |
ARAMCO |
Juaymah,
Ras Tanurah |
65 |
PP9
Extension |
Exhaust Gas Stack System including Diverter Tee Box & Duct for
12 Units Gas Turbine |
Shop
Drawing & Fabrication |
2400 |
SEC |
Riyadh |
66 |
Juba
Power Plant |
Inlet
Air Cooling Duct |
Shop
drawing and Fabrication |
190 |
SEC |
Juba |
67 |
Hail
Power Plant |
Inlet
Air Cooling Duct |
Shop
Drawing and Fabrication |
220 |
SEC |
Hail |
68 |
Shoaiba Phase 1 & 2 |
Steel
Structures for skids, headers
& Hydrants |
Shop
drawing and fabrication |
95 |
SEC |
Shoaiba |
69 |
Aramco Bulk Plants (Najran, Tabouk, Turaif, Al Jouf, Jizan, Abha) |
Steel
Building Structures, Platforms, etc. |
Shop
drawing and fabrication |
350 |
ARAMCO |
Various Locations |
70 |
Aramco Bulk Plant |
Steel
Building Structures, Platforms, etc. |
Shop
drawing and fabrication |
280 |
ARAMCO |
Madinah |
71 |
Aweer
Power Plant |
Steel
Building Structures for Transformer Sheds |
Design, Shop drawing and Fabrication |
610 |
DEWA |
Dubai |
72 |
Construction of Office Park Al Khafji
Joint Operations (Kuwait Gulf Oil Co. |
Steel
Structures |
Shop
Drawing and Fabrication |
155 |
ARAMCO |
Khafji |
73 |
Rabigh IWSP (Aramco) |
Steel
Supporting Structure for Stack and Flue Gas Stack, |
Shop
Drawing and Fabrication |
920 |
ARAMCO |
Rabigh |
74 |
Rabigh IWSP (Aramco) |
Steel
Supporting Structure & Air/Gas Duct for Boilers and Other Misc.
Structures |
Shop
Drawing and Fabrication |
4668 |
ARAMCO |
Rabigh |
75 |
Chiller Plant |
Supporting Structure for Chiller 31 meters height |
Shop
Drawing, fabrication and Installation |
3950 |
SBG |
Makkah |
76 |
Tabouk Power Plant Ext. |
Steel Building structure, Turbine Hall |
Design, Supply And installation |
583 |
SECO |
Tabouk |
77 |
Sea Water Pump House Ext. |
Steel Building structure for Pump House |
Design, Fabrication and Installation |
237 |
Royal Commission |
Yanbu |
78 |
Development of King Abdul Aziz Endowment |
Labor camp steel structure building (Truss Type) |
Design, Fabrication and installation |
300 |
SBG - PBAD |
Makkah |
79 |
Ministry of Transportation |
Steel Pedestrians bridge – 36 LM |
Design, Supply and installation |
42 |
Ministry of Transport |
Riyadh |
80 |
Official Reception Building |
Steel structure for Sky Dome 24 m dia & Metallic Structure, |
Fabrication and Installation |
233 |
Saudi Oger |
Al-Kharj |
81 |
Thumama Training center, |
Heavy trusses and sheds, |
Fabrication and Installation |
350 |
Saudi Oger |
Jeddah |
82 |
Development of King Abdul Aziz Endowment |
Hanger 20 m span with overhead Crane 20 tons capacity |
Design, Fabrication and installation |
216 |
SBG - DOKAAE |
Makkah |
83 |
Al Tufiah sub station |
Steel structure and sheds |
Design, Supply |
50 |
SECO |
Tufaih |
84 |
Tihama PP Ext. |
GIS Building Steel structure and Sheds |
Design, Supply |
100 |
SECO |
Tihama |
85 |
Najran PP Ext. |
Steel building structure, sheds and fly over platforms |
Design, Supply |
53 |
SECO |
Najran |
86 |
Jizan PP Ext. |
Steel building structure, sheds and fly over platforms |
Design, Supply |
53 |
SECO |
Jizan |
87 |
Asir PP Ext. |
Steel building structure, sheds and fly over platforms |
Design, Supply |
53 |
SECO |
Asir |
88 |
AL- Naqa sub station |
Steel Building Structure |
Supply |
15 |
SECO |
Naga |
89 |
Marwah Substation |
Steel Sliding Gate electrically operated, 8 m long. |
Supply |
15 |
SECO |
Jeddah |
90 |
Hail sub station |
Gantries 36 m high and outdoor equipment structures, |
Design, Supply |
300 |
SECO |
Hail |
91 |
Mina Slaughter House, |
Conveyor supports, steel tanks (different sizes & shapes) |
Fabrication and Installation |
169 |
B.I.L Engineering Italy |
Mina |
92 |
Tents for Hajj Pilgrims |
Steel Structures for Tents |
Fabrication and Installation |
168 |
|
Mena |
93 |
Power Plant # 9 |
2 Nos. Double Cantilever Car Parking Shelter, each 100 m long x 16 m width. |
Design, fabrication and Installation |
158 |
SECO |
Riyadh |
94 |
Power Plant # 9 |
314 Nos. GIB supports for four blocks |
Fabrication and Installation |
733 |
SECO |
Riyadh |
95 |
Power Plant # 9 |
Steel Structure buildings, Sheds, Pipe Racks, Skids, Platforms, Oil Storage tanks, etc. |
Design, Fabrication and Installation |
466 |
SECO |
Riyadh |
96 |
Power Plant # 9 |
75 meters high Transmission Tower |
Design |
65 |
SECO |
Hail |
97 |
Sawari Phase II |
Transmission Tower 36 m high, 3 Nos. Anti Explosion sliding gates and Steel Building Framing Structures, Stainless Steel Louvers and stainless steel sand traps. |
Design, Fabrication and installation |
233 |
Ministry of Defense |
Jeddah |
98 |
Beach place |
Pyramid Roof Steel Structure, 1 No. 12 X 12 x 6 meters and 2 Nos. 8 x 8 x 4 meter |
Design, Fabrication and Installation |
70 |
SBG - ABCD |
Jeddah |
99 |
Al Majed Shoping center, |
Three Levels Mezzanine floor Steel structure with metal decking |
Design, fabrication and Installation |
350 |
Hotel Are US |
Makkah |
100 |
Movinpick Hotel Madina, P130 |
20 Nos. Steel Curved bridges connecting two building and Steel Grating Walkways |
Design, Fabrication and installation |
219 |
SBG - PBAD |
Madina |
101 |
Janadriya |
Hay Storage Building Structure |
Design, Fabrication and installation |
27 |
SBG - PBAD |
Riyadh |
102 |
Taif Substation |
Steel framing structures for GIS Buildings 110 kV & 220 kV and spiral stair 18 m high |
Design, Supply |
192 |
SECO |
Taif |
103 |
E- Block PP 9 |
Pipe support structures |
Design and supply |
83 |
SECO |
Riyadh |
104 |
Safa Substation |
Steel Frames |
Design & Supply |
33 |
SECO |
Jeddah |
105 |
Al-Aous Power Plant |
Steel Frames |
Design & Supply |
25 |
SECO |
Al Aous |
106 |
Khayber Substation |
2 Nos. Gantry Steel Structure 24 m long x 16 m high each |
Design & supply |
66 |
SECO |
Khayber |
107 |
Al-Nuzha Substation |
Platforms, stairs, etc. |
Design and supply |
100 |
SECO |
Jeddah |
108 |
SAFCO IV, |
Pipe Racks and Building Structure |
Supply |
350 |
UHDE Arabia Ltd. |
Jubail |
109 |
PP7 Ext. |
Supporting Structures for Generator Circuit Breaker, System Circuit Breaker, Unit Auxiliary Transformer, |
Design and supply |
266 |
SECO |
Riyadh |
110 |
DOKAAE |
Supporting structure for Chiller Plant Compound |
Design, supply & installation |
4000 |
SBG - PBAD |
Makkah |
111 |
Shoaiba Phase 2 |
Sliding Steel Structure for Turbine Halls 6 x 12 x 30 meters. |
Fabrication |
95 |
SAS |
Shoaiba |
112 |
Construction of Office Park Al Khafji Joint Operations (Kuwait Gulf Oil Co. – Aramco Gulf Operations) |
Steel Rafters for Steel Skylight |
Shop Drawing and Fabrication |
155 |
Saudi Oger Ltd. |
Khafji |
113 |
Chiller Plant |
Pipe Supports & Pipe Riser Supports |
Design |
|
SBG - PBAD |
Makkah |
114 |
PP9 Extensions |
Steel Sunshades for Transformers & Generators |
Design |
|
Arabian Bemco Contracting Co. Ltd. |
Riyadh |
115 |
PP9 Extension |
Exhaust Gas Stack System for 12 Units Gas Turbine |
Shop Drawing & Fabrication |
1880 |
Compact, Germany |
Riyadh |
116 |
King Abdullah University for Science & Technology |
Steel Building Structures |
Shop Drawing & Fabrication |
1700 |
Saudi Oger Ltd. |
Tuwal, Jeddah |
117 |
PP # 12 - Combine Cycle Power Pant |
None |
Sub-Contract for Erection |
1700 |
Sec |
Durma - Riyadh |
118 |
PP # 10 - Combine Cycle Power Plant |
None |
Sub-Contract for Erection |
1700 |
Sec |
Riyadh |
119 |
Qurrayat Open Cycle Power Plant Extension |
None |
Sub-Contract for Erection |
1700 |
Sec |
Qurrayat |
120 |
Qassim Power Plant Extension - III
|
None |
Sub-Contract for Erection |
1700 |
Sec |
Qassim |
121 |
Qurrayah Combine Cycle Power Plant |
None |
Sub-Contract for Erection |
1700 |
Sec |
Qurrayah |
122 |
PP # 10 - Open Cycle GTG
|
None |
Sub-Contract for Erection |
1700 |
Sec |
Riyadh |
123 |
Qurrayah - Open Cycle Gas Turbine Power Plant |
None |
Sub-Contract for Erection |
1700 |
Sec |
Qurrayah |
124 |
PP # 9 - Turbine Inlet Air Cooling System for Block (F)
|
None |
Sub-Contract for Erection |
1700 |
Sec |
Riyadh |
125 |
PP # 9 - Extension III, Block F
|
None |
Sub-Contract for Erection |
1700 |
Sec |
Riyadh |
126 |
PP # 9 - Turbine Inlet Air Cooling System for Block (D)
|
None |
Sub-Contract for Erection |
1700 |
Sec |
Riyadh |
127 |
PP # 9 - Turbine Inlet Air Cooling System for Block (C)
|
None |
Sub-Contract for Erection |
1700 |
Sec |
Riyadh |
128 |
PP # 9 - Turbine Inlet Air Cooling System for Block (E)
|
None |
Sub-Contract for Erection |
1700 |
Sec |
Riyadh |
129 |
PP # 9 - Extension & Reinforcement Block C & D
|
None |
Sub-Contract for Erection |
1700 |
Sec |
Riyadh |
130 |
PP14 CC PP
|
None |
Sub-Contract for Fabrication of piping works |
1700 |
Sec |
Riyadh |
131 |
PP14 CC PP
|
None |
Sub-Contract for Fabrication of piping works |
1700 |
SEC- Saudi Aramco |
Riyadh |
132 |
HAIL- CCPP
|
None |
Sub-Contract for Fabrication of piping works |
1700 |
SEC |
HAIL |
133 |
SSPP - BEP |
None |
Sub-Contract for Fabrication of piping works |
1700 |
SEC |
JIZAN |
134 |
SANG Project - Villas
|
None |
Sub-Contract for Fabrication of Steel structure works |
70 |
SEC |
Qassim |
135 |
PP - 12 Combine Cycle
|
None |
Sub-Contract for Fabrication of piping works |
1700 |
SEC |
Durma - Riyadh |
136 |
PP - 12 Combine Cycle
|
None |
Sub-Contract for Fabrication of Steel structure works |
1200 |
SEC |
Durma - Riyadh |
137 |
PP - 10 Combine Cycle
|
None |
Sub-Contract for Fabrication of piping works |
1700 |
SEC |
Riyadh |
138 |
PP - 10 Combine Cycle
|
None |
Sub-Contract for Fabrication of Steel structure, Stacks & Skid Frames works. |
5500 |
SEC |
Riyadh |
139 |
Qurrayah Combine Cycle Power Plan |
None |
Sub-Contract for Fabrication of piping works |
1700 |
SEC |
Qurayyah - KSA Eastern Province |
140 |
Qurrayah Combine Cycle Power Plan
|
None |
Sub-Contract for Fabrication of Steel structure works |
1500 |
SEC |
Qurayyah - KSA Eastern Province |